A customer is planning for a new large x3850 X5 server installation. Which of the following steps should the technical specialist take to ensure success?
A. Conduct a TDA
B. Create an implementation plan
C. Provide detailed TCO analysis
D. Engage local FTSS for implementation
Answer: A